Construction Season 2020 - What is happening on site?

Share on Facebook Share on Twitter Share on Linkedin Email this link

Do you have any questions or concerns about traffic control measures on the Alaska Highway through the Hillcrest area? Please contact our Traffic Facilitator, Dave Legault at 867-334-2775. David is happy to help answer your questions and address your concerns.

In short, this two year Contract has been divided into two phases: Phase 1 and Phase 2. A drawing of the project area showing the demarcation line between the two phases can be viewed here.

Phase One shall be completed in year 2020 and will comprise of full (four lane) reconstruction and paving/paint marking of the Alaska Highway #1 from km 1421.8 to km 1423.2, including signalization of the Hillcrest Drive intersection. West frontage road construction/paving will be completed in Phase One and limited to the area between Hillcrest Drive and approximately 100 metres north of Roundel Road. East frontage road work/paving will be completed in year 2020. The storm sewer system including all highway crossings shall be completed and operational in 2020. Water Main construction in Phase One will include the highway crossing at km 1423.07.

There may be opportunities for the Contractor to perform some Phase Two work in the 2020 construction season. Phase Two work is located between km 1423.2 and 1424.2 and includes right-of-way excavation, highway embankment and trail construction work.

Do you have any questions or concerns about traffic control measures on the Alaska Highway through the Hillcrest area? Please contact our Traffic Facilitator, Dave Legault at 867-334-2775. David is happy to help answer your questions and address your concerns.

In short, this two year Contract has been divided into two phases: Phase 1 and Phase 2. A drawing of the project area showing the demarcation line between the two phases can be viewed here.

Phase One shall be completed in year 2020 and will comprise of full (four lane) reconstruction and paving/paint marking of the Alaska Highway #1 from km 1421.8 to km 1423.2, including signalization of the Hillcrest Drive intersection. West frontage road construction/paving will be completed in Phase One and limited to the area between Hillcrest Drive and approximately 100 metres north of Roundel Road. East frontage road work/paving will be completed in year 2020. The storm sewer system including all highway crossings shall be completed and operational in 2020. Water Main construction in Phase One will include the highway crossing at km 1423.07.

There may be opportunities for the Contractor to perform some Phase Two work in the 2020 construction season. Phase Two work is located between km 1423.2 and 1424.2 and includes right-of-way excavation, highway embankment and trail construction work.